Transpetro vessel construction lifts Brazil shipyard jobs
Transpetro vessel construction began 15 Oct 2026 as Estaleiro Rio Grande laid the keel for the first of 13 Ecovix-built ships worth US$278M.

The ceremony in Rio Grande do Sul marked the formal start of a 13-vessel order placed with Ecovix, the industrial group operating the yard. Transpetro, the logistics subsidiary of Petrobras, signed the four-Handymax contract in February 2025. The contract was valued at US$278 million, or US$69.5 million per vessel. Steel processing for the first hull had begun in April 2026.
The Mar Aberto programme targets the renewal and expansion of Transpetro’s own fleet. It also connects domestic industrial output with the fuel-transport requirements of Brazil’s growing oil system. The order gives the shipbuilding sector a visible multi-year pipeline after a prolonged period of reduced activity.
A fleet built for refined products and gas
The 13 vessels fall into three groups. Ecovix will build four Handymax tankers to carry refined products, including marine diesel, S10 diesel, S500 diesel and aviation gasoline. Five pressurised tankers will transport liquefied petroleum gas and related derivatives. Four MR1 vessels will handle medium-range fuel movements between Brazilian ports and terminals.
By FurtherBrazil’s reading of the numbers, the breakdown below captures the full scope of the programme, as reported in October 2026.
| Vessel group | Number ordered | Primary cargo |
|---|---|---|
| Handymax tankers | 4 | Refined petroleum products |
| Pressurised tankers | 5 | Liquefied petroleum gas and derivatives |
| MR1 vessels | 4 | Medium-range fuel transport |
Together, the orders spread production risk across three cargo categories and secure Transpetro’s operating capacity well into the next decade.
What does the deal mean for investors?
The supply chain is already moving. Estaleiro Rio Grande received 11,000 tonnes of steel from Indonesia in July 2026. By 15 October 2026, more than 65% of the equipment required for construction had been procured, according to trade publication Portos e Navios.
Workforce numbers signal the scale of the industrial commitment. The yard had mobilised more than 500 professionals during 2026. It expects approximately 1,000 workers by the end of 2026 and around 1,700 in 2027 as the remaining vessels enter production. That growth makes Estaleiro Rio Grande one of the more active maritime employment centres in southern Brazil.
Robson Passos, chief executive of Ecovix, described the keel-laying as a resumption of naval industrial activity in Brazil, in comments reported on 15 October 2026 by Agência Brasil and Jornal do Comércio.
The crisp analytical read is this: a contracted order, a funded supply chain and a rising headcount together indicate that execution risk here is lower than the sector average for comparable Latin American shipbuilding projects.
Pressurised-tanker construction is scheduled to begin in early 2027. Investors and port operators tracking Brazil’s maritime fuel logistics should monitor that milestone closely, along with Transpetro’s next fleet-capacity announcements under the Mar Aberto framework.
Quick answers
Transpetro ordered 13 vessels in total: four Handymax tankers, five pressurised tankers and four MR1 vessels, all to be built by Ecovix at Estaleiro Rio Grande in Rio Grande do Sul.
The four-Handymax contract was signed in February 2025 and valued at US$278 million, equivalent to US$69.5 million per vessel.
The yard had mobilised more than 500 professionals by October 2026 and expects approximately 1,700 workers by 2027 as additional vessels enter production.