Southern Copper Peru plans US$10.3B expansion
Southern Copper Peru targets US$10.3B across four projects by 2032, adding up to 530,000 tonnes of annual copper output.

The programme spans Arequipa, Apurímac, Cajamarca and Moquegua. Each project has its own investment figure and timetable. Together, they represent one of the most ambitious copper development programmes in South America today.
A large pipeline across Peru
Tía María, in Arequipa, was 49.6% complete as of 30 September 2026, per the company’s third-quarter 2026 update. Southern Copper had invested US$884.3M by that date. The company has committed approximately US$1.1B for related procurement and contracts.
Production at Tía María is scheduled to begin in the first half of 2028. Delays to mechanical assembly and engineering work pushed back the original timeline. The mine is expected to yield approximately 120,000 tonnes of copper cathodes annually in its early operating years.
Los Chancas, in Apurímac, carries an estimated cost of US$2.6B. Southern Copper targets first production in 2031. The mine would generate around 130,000 tonnes of copper per year at steady state.
Michiquillay, in Cajamarca, would require approximately US$2.5B, according to company project estimates reported in October 2026. Start-up is targeted for 2032. Annual output is projected at 225,000 tonnes, making it the largest of the four projects by production volume.
What does the Cuajone expansion add?
The fourth element is a proposed US$680M capacity increase at the existing Cuajone mine. Southern Copper is evaluating a rise in milling capacity from 90,000 to 120,000 tonnes per day. That 33% increase could yield an average of 55,000 additional tonnes of copper annually. The expansion would require new mining equipment and an additional production line at the concentrator.
By FurtherBrazil’s reading of the numbers, the four projects together could add up to 530,000 tonnes of annual copper capacity once all reach steady state, a substantial increment against current Peruvian output.
Southern Copper’s Peruvian mines produced 114,846 tonnes of copper in the third quarter of 2026, down 6.1% year on year, according to the company’s Q3 2026 filing. Lower ore grades and recoveries at Toquepala and Cuajone drove the decline. Globally, the company produced 693,602 tonnes during the first nine months of 2026 (a 2.9% fall year on year), with Peru accounting for the bulk of the shortfall.
The Cuajone study therefore addresses a real operational gap. It also reflects the capital intensity common to large Latin American resource projects, comparable in scale to Anglo American’s Minas-Rio iron ore ramp-up in Brazil.
What does the pipeline mean for investors?
Copper demand projections, driven in part by electric-vehicle supply chains (a theme explored in our coverage of BYD’s Brazilian EV expansion), reinforce the strategic logic behind the spend. Timing depends on permitting progress, construction execution and local social agreements.
Tía María’s 49.6% completion rate signals the most advanced position in the pipeline. Los Chancas and Michiquillay offer greater production upside but remain further from operations, with corresponding exposure to development risk.
| Project | Investment | Target start | Annual copper output |
|---|---|---|---|
| Tía María | US$884.3M invested; ~US$1.1B committed | H1 2028 | ~120,000 t cathodes |
| Los Chancas | US$2.6B | 2031 | 130,000 t |
| Michiquillay | US$2.5B | 2032 | 225,000 t |
| Cuajone expansion | US$680M | Under evaluation | ~55,000 t additional |
Source: Southern Copper’s Q3 and nine-month 2026 results and earnings disclosures. Investors should track Tía María’s commissioning schedule, Los Chancas permitting and Michiquillay’s social licence progress, as those milestones will determine how quickly the pipeline converts project estimates into operating copper capacity.
What it means for Brazil
Southern Copper’s US$10.3B Peruvian pipeline intensifies competition for the capital and engineering talent that Brazil’s own mining sector is courting. The scale is comparable to the momentum seen at Anglo American’s Minas-Rio operation, where iron ore output jumped 24% year on year in Q3 2026, yet copper’s trajectory is being shaped increasingly by EV demand.
That EV link matters directly for Brazil. BYD’s Camaçari plant, which has assembled over 100,000 vehicles, is among the end-market forces driving copper demand growth across South America. If Peru’s projected 530,000 additional tonnes of annual copper capacity reaches the market by the early 2030s, Brazilian policymakers and industrialists will need to monitor how regional supply shifts affect input costs and investment flows into Brazil’s own critical-minerals ambitions.
Quick answers
Southern Copper has outlined a US$10.3B pipeline across four Peruvian projects: Tía María, Los Chancas, Michiquillay and the Cuajone expansion, according to the company’s Q3 2026 disclosures.
Tía María is scheduled to begin production in the first half of 2028. The project was 49.6% complete as of 30 September 2026, with US$884.3M already invested.
At steady state, the four projects could collectively add up to 530,000 tonnes of annual copper capacity, with Michiquillay alone targeting 225,000 tonnes per year from 2032.